Project description

A wind farm with 13 2 MW turbines for a total of 26 MW was built in Puglia, in the Province of Foggia, between Lucera and Troia.

CEAS designed the local road system, the service roads and the crane platforms used for assembling the turbines, as well as the whole cable duct of about 29 km.

CEAS also designed the building used as power substation, with low and medium voltage electric panels and a transformer. The foundations for the electromechanical equipment (switches, disconnectors, etc. …) and for the high voltage transformer were built outside the building.

The executive design of the turbine foundations was particularly important. It required a very accurate deformation analysis, in compliance with the maximum subsidence imposed by the turbine manufacturers.